18.02.2022
Contract Award Notice
Contract No.TJ NHPP CS 17: Consulting Services for Preparation of Emergency Preparedness Plan for Vakhsh Cascade
Project Name: Nurek Hydropower Rehabilitation Project, Phase 1
05.07.2021
Invitation for tenders two stage
Supply and Installation of Billing and Metering Infrastructure and Rehabilitation of Distribution Lines 0.4 KV Single Circuit ABC in the Cities of Kulob and Bokhtar Including Surroundings
The World Bank has agreed to provide financing under the Nurek Hydropower Rehabilitation Project to Barqi Tojik to carry out the necessary techno-economic studies and assessments for new Tajikistan-Afghanistan high voltage interconnection line project.
19.03.2021
Consulting services for: preparation of emergency preparedness plan for Vakhsh Cascade
At the request of the Government of Tajikistan (GoRT), the World Bank has agreed to finance preparation of an Emergency Preparedness Plan (EPP) for the Vakhsh Cascade in Tajikistan under the Nurek Hydropower Rehabilitation Project.
05.01.2021
REQUEST FOR PROPOSAL
In the frame of this contract it is planned to dismantle the generator
REQUEST FOR EXPRESSIONS OF INTEREST (with extended deadline). Consulting services for: feasibility study for rehabilitation of the Baipaza HPP
23.07.2020
Supply of office equipment and associated supplies for PRG ELRP of OSHC Barqi Tojik
Request for expressions of interest supply of office equipment and associated supplies for PRG ELRP of OSHC Barqi Tojik in the frame of Nurek Rehabilitation Project, Phase 1
27.07.2020
Audit of the OSHC “Barqi Tajik” and PRG Energy Loss Reduction
REQUEST FOR EXPRESSIONS OF INTEREST for audit of the OSHC “Barqi Tajik” and PRG Energy Loss Reduction for the fiscal year ending December 31, 2020
Terms of reference for the audit of OSHC “Barqi Tojik” and Nurek hydropower rehabilitation Project Phase 1 for the fiscal year ending december 31, 2020
21.07.2020
Consulting services for: feasibility study for rehabilitation of the Baipaza HPP
REQUEST FOR EXPRESSIONS OF INTEREST. Consulting Services for: Feasibility Study for Rehabilitation of the Baipaza Hydropower Plant
21.07.2020
Terms of Reference_Rehabilitation of the Baipaza HPP. Feasibility Study
Terms of Reference. Rehabilitation of the Baipaza Hydropower Plant. Feasibility Study
10.07.2020
Contract Award Publication Contract No. TJ NHPP RFB P2.1 - Dam Safety Investigations and Monitoring
Rehabilitation of Nurek Hydropower Plant Project. TJ NHPP RFB P2.1 - Dam Safety Investigations and Monitoring
10.07.2020
Contract Award Publication Contract No. TJ NHPP RFB P3 - Hydromechanical Equipment
Rehabilitation of Nurek Hydropower Plant Project TJ NHPP RFB P3 - Hydromechanical Equipment |
25.05.2020
STAKEHOLDER ENGAGEMENT PLAN (Final)
STAKEHOLDER ENGAGEMENT PLAN
Nurek Hydropower Rehabilitation Project Phase 2
Republic of Tajikistan
25.05.2020
Environmental & Social Impact Assessment and Environmental & Social Management Plan
Environmental & Social Impact Assessment and Environmental & Social Management Plan
Nurek Hydropower Rehabilitation Project Phase 2
Republic of Tajikistan
25.05.2020
Environmental and Social Impact Assessment (Final)
Environmental and Social. Impact Assessment. Nurek Hydropower Rehabilitation Project Phase 2
Republic of Tajikistan
25.05.2020
Environmental and Social Management Plan (Final)
Environmental and Social Management Plan. Nurek Bridge Rehabilitation. Nurek Hydropower Rehabilitation Project
28.04.2020
Draft Updated Nurek ESIA
Environmental and Social Impact Assessment >>>>>>
17.04.2020
Contract Award Publication Contract No. TJ NHPP RFB P4 - Switchyard
Execution design for replacement of six autotransformers, refurbishment and partial replacement of various high voltage equipment and ancillary systems.
Decontamination of structures with respect to rehabilitation of equipment.
Supply of new equipment and spare parts including shipping to site.
Dismantling of existing equipment, erection and commissioning of new equipment, one group of three single-phase autotransformers at a time, with minimized impact on power plant operation and power production.
Associated civil works.
Supply of new equipment and spare parts including shipping to site.
04.07.2019
Nurek hydropower rehabilitation project. Phase 1
The Republic of Tajikistan has applied for financing from the World Bank International Development Association, Asian Infrastructure Investment Bank and Eurasian Fund for Stabilization and Development (EFSD) toward the cost of the “Nurek hydropower rehabilitation project. Phase I.”, and intends to apply part of the proceeds toward payments under the Contract for Rehabilitation of Switchyard.