18.02.2022 Contract Award Notice

Contract No.TJ NHPP CS 17: Consulting Services for Preparation of Emergency Preparedness Plan for Vakhsh Cascade

Project Name: Nurek Hydropower Rehabilitation Project, Phase 1

05.07.2021 Invitation for tenders two stage

Supply and Installation of Billing and Metering Infrastructure and Rehabilitation of Distribution Lines 0.4 KV Single Circuit ABC in the Cities of Kulob and Bokhtar Including Surroundings

06.05.2021 Consulting services for: Feasibility study for new Tajikistan-Afghanistan high voltage interconnection line

The World Bank has agreed to provide financing under the Nurek Hydropower Rehabilitation Project to Barqi Tojik to carry out the necessary techno-economic studies and assessments for new Tajikistan-Afghanistan high voltage interconnection line project. 

19.03.2021 Consulting services for: preparation of emergency preparedness plan for Vakhsh Cascade

At the request of the Government of Tajikistan (GoRT), the World Bank has agreed to finance preparation of an Emergency Preparedness Plan (EPP) for the Vakhsh Cascade in Tajikistan under the Nurek Hydropower Rehabilitation Project.

05.01.2021 REQUEST FOR PROPOSAL
In the frame of this contract it is planned to dismantle the generator

05.08.2020 Consulting services for: feasibility study for rehabilitation of the Baipaza HPP (extension of the term until 12.08)

REQUEST FOR EXPRESSIONS OF INTEREST (with extended deadline). Consulting services for: feasibility study for rehabilitation of the Baipaza HPP

23.07.2020 Supply of office equipment and associated supplies for PRG ELRP of OSHC Barqi Tojik

Request for expressions of interest supply of office equipment and associated supplies for PRG ELRP of OSHC Barqi Tojik in the frame of Nurek Rehabilitation Project, Phase 1 

27.07.2020 Audit of the OSHC “Barqi Tajik” and PRG Energy Loss Reduction

REQUEST FOR EXPRESSIONS OF INTEREST for audit of the OSHC “Barqi Tajik” and PRG Energy Loss Reduction for the fiscal year ending December 31, 2020

27.07.2020 Terms of reference for the audit of OSHC “Barqi Tojik” and Nurek hydropower rehabilitation Project Phase 1

Terms of reference for the audit of OSHC “Barqi Tojik” and Nurek hydropower rehabilitation Project Phase 1 for the fiscal year ending december 31, 2020

21.07.2020 Consulting services for: feasibility study for rehabilitation of the Baipaza HPP

REQUEST FOR EXPRESSIONS OF INTEREST. Consulting Services for: Feasibility Study for Rehabilitation of the Baipaza Hydropower Plant

21.07.2020 Terms of Reference_Rehabilitation of the Baipaza HPP. Feasibility Study

Terms of Reference. Rehabilitation of the Baipaza Hydropower Plant. Feasibility Study 

10.07.2020 Contract Award Publication Contract No. TJ NHPP RFB P2.1 - Dam Safety Investigations and Monitoring
Rehabilitation of Nurek Hydropower Plant Project. TJ NHPP RFB P2.1 - Dam Safety Investigations and Monitoring

10.07.2020 Contract Award Publication Contract No. TJ NHPP RFB P3 - Hydromechanical Equipment

Rehabilitation of Nurek Hydropower Plant Project TJ NHPP RFB P3 - Hydromechanical Equipment


25.05.2020 STAKEHOLDER ENGAGEMENT PLAN (Final)
STAKEHOLDER ENGAGEMENT PLAN
Nurek Hydropower Rehabilitation Project Phase 2
Republic of Tajikistan

25.05.2020 Environmental & Social Impact Assessment and Environmental & Social Management Plan
Environmental & Social Impact Assessment and Environmental & Social Management Plan
Nurek Hydropower Rehabilitation Project Phase 2
Republic of Tajikistan

25.05.2020 Environmental and Social Impact Assessment (Final)
Environmental and Social. Impact Assessment. Nurek Hydropower Rehabilitation Project Phase 2
Republic of Tajikistan

25.05.2020 Environmental and Social Management Plan (Final)
Environmental and Social Management Plan. Nurek Bridge Rehabilitation. Nurek Hydropower Rehabilitation Project

28.04.2020 Draft Updated Nurek ESIA
Environmental and Social Impact Assessment >>>>>>

17.04.2020 Contract Award Publication Contract No. TJ NHPP RFB P4 - Switchyard

Execution design for replacement of six autotransformers, refurbishment and partial replacement of various high voltage equipment and ancillary systems.

Decontamination of structures with respect to rehabilitation of equipment.

Supply of new equipment and spare parts including shipping to site.

Dismantling of existing equipment, erection and commissioning of new equipment, one group of three single-phase autotransformers at a time, with minimized impact on power plant operation and power production.

Associated civil works.

Supply of new equipment and spare parts including shipping to site.

04.07.2019 Nurek hydropower rehabilitation project. Phase 1

       The Republic of Tajikistan has applied for financing from the World Bank International Development Association, Asian Infrastructure Investment Bank and Eurasian Fund for Stabilization and Development (EFSD) toward the cost of the “Nurek hydropower rehabilitation project. Phase I.”, and intends to apply part of the proceeds toward payments under the Contract for Rehabilitation of Switchyard.